File #: ID 25-4189    Version: 1 Name: Beam Construction Design/Build Contract for Sheriff’s Office Upfit ProjectRenovation/Expansion Project - Phase 1 Update
Type: Action Item Status: New Business
File created: 6/17/2025 In control: Board of Commissioners
On agenda: 7/7/2025 Final action:
Title: Beam Construction Design/Build Contract for Sheriff's Office Upfit Project
Attachments: 1. AIA-Beam-Phase 1- Final

 

Meeting Date:                     July 7, 2025

 

Title

Beam Construction Design/Build Contract for Sheriff’s Office Upfit Project

body

 

Summary:

summary

 

Earlier this year, the Planning Department conducted a Request for Qualifications (RFQ) process. Four applicants submitted packages, which were scored and followed by interviews. Beam Construction, in partnership with CBSA as the project designer, was ultimately selected. Staff has completed contract negotiations and now presents the attached contract for phase one of the Design Building contract for Commissioner approval.

 

Phase 1 Contract is to include:

Preconstruction design services = $115,600.00

Roof Allowance (Cafeteria) = $125,000.00

Roof Allowance (6th Grade Building) = $75,000.00

Utility Allowance (Separate gas, water, sewer from schools) = $25,000.00

Phase 1 TOTAL = $340,600.00

 

It is important to note that this project is a critical step in moving forward with the planned Detention Center renovations, which will require the Sheriff's administrative staff to vacate the existing facility. Additionally, the upfit of the former 6th grade building will allow the entire Sheriff’s Office to operate under one roof, offering significant operational benefits.

 

Funding:
This project requires
no local funding. It will be fully funded through Legislative grant funds.

 

body

Budget:

 

N/A

 

Contact Information:

 

Aubrey Clay, Rutherford County Project Manager

aubrey.clay@rutherfordcountync.gov <mailto:aubrey.clay@rutherfordcountync.gov>

828-287-6052

 

Recommended Motion:

recommended action


Approve
this Phase One Design/Build contract with Beam Construction and authorize a Notice to Proceed for this project.