Meeting Date: June 1, 2026
Title
Vannoy/Moseley Construction Agreement for Rutherford County Detention Center
body
Summary:
summary
Rutherford County continues to work with the design/build team of Vannoy Construction and Moseley Design on the renovation project for the Rutherford County Detention Facility.
Over the past several months, Vannoy/Moseley has collaborated with the County on Phase 2 of the project design, which included the completion of Construction Document Drawings and Specifications, review and approval by the North Carolina Department of Health Service Regulation (NCDHSR), bidding, and establishment of the Guaranteed Maximum Price (GMP).
The project is now ready to move into the construction phase.
body
Budget:
Construction Amendment Proposal
• Base Bid - $7,863,394
• Alternate #1 (Group Shower Exhaust and Ceilings) - $179,403
• Alternate #3 (Front Entry Gate) - $40,295
• Alternate #4 (Back Sallyport) - $59,902
• Alternate #5 (DOAS-1 Replacement) - $323,017
• Alternate #6 (Multipurpose Room Build) - Approximate - $45,000
Contact Information:
Aubrey Clay, Rutherford County Project Manager
aubrey.clay@rutherfordcountync.gov <mailto:aubrey.clay@rutherfordcountync.gov>
828-287-6052
Project Overview and Budget Presentation:
Stephen Boyd, Preconstruction Manager, Vannoy Construction
Recommended Motion:
recommended action
Authorize the Interim County Manager and the County Attorney to negotiate terms of contract and authorize the County Manager, Finance Officer, Clerk to the Board, and other County officials to sign and execute all documents in support of this action.